2016 – Execution of protection system with guide rails for Puentes Y Calzadas Infraestructuras S.L
Project Details
Beneficiary: Puentes Y Calzadas Infraestructuras S.L
Duration: April 2016 – December 2016
Project Description
- Level crossing km 283 + 424 – Line Bucuresti-Timisoara, junction of Butoiesti – Strehaia, km 305 + 662,20
- Level crossing km 288 + 586 – Line Strehaia – Motru, intersection Strehaia – Jirov, km 1 + 357
Main Works:
- Welded rails stress relief – 0.12 km;
- Removal of rails from concrete sleepers – 0.156 km;
- Manual sifting of ballast material – 77.5 m3;
- Replacement of plated concrete sleepers – 296 pcs.;
- Track installation – 0.18 km;
- Ballast profiling with additional material – 120 m3;
- Tamping I, II and III of concrete sleepers on new, manually placed bedding – 580 pcs.;
- Aluminothermic welding of rails – 18 pcs.;
- Making of guard rail ends. Making of 49/60 transition rails – 8 pcs.;
- Installation of guard rails – 282 m;