2015 – Construction works in the area of SRCF Galati

Project Details

Beneficiary: National Railway Company “CFR” S.A., Regional Office Galati
Duration: August 2015 – December 2015

Project Description

  • Repais of continuous welded rails (CWR) and electrical welding – 3 Lots

Main Works:

  • Electrical welding of rails and building of continuous welded rails (CWR) – 3.563 m;
  • Manufacturing and replacement of glued insulated joints – 62 pcs.;
  • Aluminothermic welding of joint of turnouts – 751 pcs.;
  • Realising of turnouts and embedding in continuous welded rails (CWR) – 53 pcs.;