2015 – Construction works in the area of SRCF Constanta

Project Details

Beneficiary: National Railway Company “CFR” S.A., Regional Office Constanta
Duration: June 2015 – December 2015

Project Description

  • Repair and maintenance works of IVth Paneuropean Corridor – Tronson Lehliu – Constanta
  • Repais of continuous welded rails (CWR) and electrical welding of rails line 813 Constanta – Mangalia
  • Repair works of railways to eliminate the speed limitation Line 804 Tandarei-Movila

Main Works:

  • Replacement of rails – 9.333 m;
  • Aluminothermic welds – 373 pcs.;
  • Realising and building of continuous welded rails (CWR) – 12.700 m;
  • Manufacturing and replacement of glued insulated joints – 41 pcs.;
  • Replacement of spare parts on turnouts (including welding) – 3 pcs.;
  • Replacement of glued insulated joints – 4 pcs.;
  • Replacement of defect concrete sleepers – 3.281 m;
  • Welding of rails and building of continuous welded rails (CWR) – 3.100 m;