2012 – Maintenance and repair works Corridor IV Pan-European, Bucharest-Campina section
Project Details
Beneficiary: National Railway Company “CFR” S.A., Regional Office Bucharest
Duration: October 2012 – December 2012
Main Works:
- Replacement of 60-1/9-300 simple switch frogs– 3 pcs.;
- De-stressing– 21.280 m;
- Thermit welding– 360 pcs.;
- Switches and crossings part replacement– 6 pcs.;
- Replacement of 60E1 glued insulated rail joints– 136 pcs.;
- Replacement of 60E1 track– 300 m;
- Clearing vegetation– 36.300 sqm;