2005 – Rehabilitation of the Pan-European Corridor IV – Chitila station

Project Details

Beneficiary: National Railway Company “CFR” S.A., Regional Office Bucharest
Duration: 2005

Project Description

Wiebe Romania participated in 2005 in completing the rehabilitation of the railway substructure and superstructure in the station of Chitila, as part of the project “Upgrade of the Bucharest – Campina railway for speeds up to 160 km/h – a component of the Pan-European Corridor IV.”

Embankment works, including strengthening with geogrind and geotextile material, draining works, railway superstructure and turnouts.

« 1 of 4 »

© 2021 Wiebe Romania. All rights reserved. Webmail