2005 – Embankment works on the Arges River

Project Details

Beneficiary: National Railway Company “CFR” S.A., Regional Office Bucharest
Duration: August 2005 – September 2005

Project Description

The heavy rains in 2005 damaged the transportation and communication infrastructures in Romania.

Wiebe Romania was invited to participate in restoring the safety of railway structures in the Bucharest Railway District area. The works implemented included embankment works to protect the bridge substructure, river diversion and bank protection works for the Gradistea bridge on Arges River, km 23+577, Phase I.

Main Works:

  • Excavations in the river bed – 1.475 m3;
  • Excavations of working platform – 1.495 m3;
  • Work platform and geogrid reinforcement – 8.262 m3 / 1.050 m2;